25Think Tank Summit: A Cleaner Ward with a Smarter Waste Route
The year ends with a summit. Each team draws the lanes around the school as a network, estimates how much waste the households produce, and plans a collection route that covers every lane with as little repeated travel as possible. They check the van capacity, estimate the number of trips and the time needed, and then present their plan together with the best of their work from the year to parents and local guests.
- Class and age
- Class 9 · 14–15
- Activity type
- Group
- Time needed
- 3 sessions of 60 minutes plus the summit
- Difficulty
- Challenging
- Estimated budget
- ৳0–৳100
Mathematical concepts
- Networks (graphs): junctions and lanes
- Degree of a junction; odd and even junctions
- Routes that use every lane once
- Rates, capacity and estimation
- Combining models into one plan
Learning objectives
- Represent a real place as a network.
- Use odd and even junctions to plan an efficient route.
- Estimate waste, trips and time from data.
- Present a complete, well-argued plan.
Real-life connection
City corporations plan waste collection, postal delivery, street cleaning and snow clearing routes using network mathematics. A shorter route saves fuel, time and money and keeps streets cleaner.
Materials required
- A sketch map of the lanes around the school (from project 13 if available)
- Chart paper, coloured pens
- Calculator
- Display boards for the summit
Step-by-step instructions
- Draw the lanes as a network: dots for junctions, lines for lanes, with each lane length marked.
- Count the lanes at each junction (its degree) and mark the odd junctions.
- If there are 0 or 2 odd junctions, find a route that uses every lane exactly once. If there are more, pair up odd junctions and repeat the shortest lanes between them.
- Estimate waste: count households in each lane and use an agreed amount per household per day (measure it at home for a week if possible).
- Compare the total with the van capacity to find the number of trips. Estimate the time from the route length and an average speed.
- Improve the plan: where should the dumping point be? Could two smaller routes be better?
- Prepare a summit board: the network, route, calculations and recommendations.
- At the summit, present this plan and one favourite project from the year, and answer guests’ questions.
Mathematical explanation
Every time a route passes through a junction it uses one lane in and one lane out, so junctions on a route that uses each lane once must have an even number of lanes, except possibly the start and the end. That is why a network with 0 or 2 odd junctions can be covered without repeating, and any other network needs some lanes repeated. Pairing the odd junctions to repeat the least total length gives the shortest route. Waste estimates follow from rates: for example 240 households × 1.5 kg per day = 360 kg, which fits one 500 kg van trip, but doubles on festival days. Combining these models turns a messy problem into a plan people can act on.
Expected project output
A network map with an efficient route, waste and trip calculations, recommendations and a summit display board.
Skills developed
- Network modelling
- Estimation from data
- Systems thinking
- Public presentation
Assessment criteria
- The network represents the area accurately.
- Odd junctions are identified and the route is efficient.
- Waste, trips and time are estimated with clear assumptions.
- The summit presentation is clear and answers questions well.
Extension challenge
Add a recycling plan: if half of the waste is food scraps that could become compost, how does that change the number of trips and the cost?
Safety and inclusion
Survey lanes only in groups with an adult and stay off busy roads. Do not handle waste with bare hands; if you weigh household waste at home, use gloves and wash your hands.